How to Compare Framing and Building System Quotes in Ontario: Level of Completion First, the Thirteen-Line Grid, and Three Framing Quotes for the Same House Added Up

Framing & Building Systems

Comparing Framing Quotes: Find Out What You Are Buying Before You Find Out What It Costs

Three numbers land on the kitchen table: $33,600, $81,000 and $96,000 to frame the same house. The instinct is to call the cheap one. Hold off: they are almost never quoting the same job. This page sorts quotes by level of completion first, then runs them through a thirteen-line grid, then adds up three example framing quotes until they are the same job.

Level First, Price Second

Every quote for a house structure sits at one of five levels. Mixing them up is the most expensive mistake on this page, so sort them before you look at a total.

LevelWhat it isA real published examplePrice
Level 1, kit or materialsWhat the supplier makes or shipsAn Ontario SIP package seller, 2,400 sq ft, wall and roof panels delivered$89,500
Level 1, kit or materialsSameA Quebec log kit maker, 2,544 sq ft model, log and beam kit, April 2025 list$126,472
Level 2, installed structureKit plus delivery, equipment and assemblyWood framing, labour and materials, 2,400 sq ft at our $40 planning number$96,000
Level 3, closed-in shellStructure plus roof, sheathing, wraps, windows, exterior doorsRarely published on its own; ask for itquoted per job
Level 3 to 4Modular house set on your foundationAn Ontario prefab cottage seller, 2,125 sq ft, delivered and installed, foundation extra$629,500
Level 4, finished houseEverything to move in, no land or siteA Simcoe County custom builder, straightforward house$400 to $500 a sq ft
Level 5, complete propertyLevel 4 plus septic, well, hydro, driveway, permits, chargesDepends on the lotquoted per lot

October 2026 unless dated, before HST. The SIP package excludes assembly and the foundation; it works out to about $37 a sq ft by our arithmetic ($89,500 / 2,400). The log list does not say what each kit level includes. The modular price works out to about $296 a sq ft.

Why Ontario prices are all over the map: the framing contractors, suppliers and price guides we checked for this page could not agree on what framing costs, partly because they were not pricing the same thing. A Canadian proptech blog put framing with materials at $11 a sq ft; a Canadian finance guide said $30 to $60. Per house, a proptech blog had $22,000 for 2,000 sq ft and a national marketplace said up to $160,000, size not stated. Level of completion, floor area versus footprint, and what is “by others” make the gap. Budget $40 a sq ft of floor, labour and materials, and get two or three quotes on the same written scope.

Say it bluntly: a $89,500 SIP package and a $96,000 framing quote are not $6,500 apart. The SIP package has nobody to stand the panels up, and there is no independent published price for that labour. Bring every quote to Level 4 before you compare; the kit versus finished house page shows how, and the kit to finished house calculator does the adding. The SIP page covers the panels themselves.

The Thirteen Lines

LineWhat the quote has to sayIf it is missing, budget
1. Level of completionLabour only, labour and materials, closed in, or moreNothing until you know
2. Measured areaFloor area or footprint; basement, garage, porch counted or notRecalculate at the same area
3. Lumber packageSupplied or not, from whose takeoff, price held how long$25,000 to $60,000, a finance guide, size not stated
4. Roof trussesSupplied, delivered, set; girders and hips included$5 to $9 a ft of span per truss
5. Engineered floorI-joists or floor trusses, supplied or set onlyI-joists $4 to $9 a lineal ft (thin); packages quoted per job
6. BeamsEach LVL, steel or glulam beam listed, supplied and setLVL installed $800 to $2,500 typical
7. SheathingWalls, roof, subfloor; glued and screwed or notAsk your yard; we do not print a sheet price
8. WrapsHouse wrap, taped seams, window flashingQuoted per job
9. Windows setInstalled by the framer, or “by others”Quoted per job
10. Crane or boom truckWho books and pays, how many hours$700 to $1,500 a day; half day $900 to $1,400
11. EngineeringBeam sizing, truss drawings, bracing on the plansEngineer $150 to $300 an hour
12. PermitsWho applies, who books the framing inspectionYour municipality’s fee
13. CleanupDumpster, scrap, sweeping the slabQuoted per job

October 2026, before HST. Truss figures are from two Canadian calculator sites; a simple gable roof of 25 to 35 trusses at 30 to 36 ft span works out to about $3,750 to $11,300 before girders, hips and delivery, our estimate. The I-joist figure is from a calculator site with no named data. The full framing numbers are on the house framing cost page.

Three Example Quotes on the Grid

This is a made-up example. A two-storey house, 1,200 sq ft footprint, 2,400 sq ft of floor, engineered floors, two LVL beams, a simple gable roof of 30 trusses at a 32 ft span. Three fictional framers quote it, priced with the ranges on this page.

LineQuote AQuote BQuote C
Price on paper$33,600$81,000$96,000
LevelLevel 2, labour onlyLevel 2, labour and materialsLevel 2, plus wraps and windows set
Lumber, sheathing, engineered floorBy owner: add $42,500 allowanceIncludedIncluded
TrussesBy owner: add 30 x 32 x $7 = $6,720IncludedIncluded
Two LVL beamsIn the lumber allowanceNot listed: add 2 x $1,650 = $3,300Included
Boom truck, half dayNot listed: add $1,150“By others”: add $1,150Included
Wraps, windows set, dumpsterNot includedNot includedIncluded
Same priced scope$83,970$85,450$96,000

Example only. The lumber allowance is the middle of the finance guide’s $25,000 to $60,000, which does not say what it covers; the truss rate is the middle of $5 to $9; each LVL is the middle of $800 to $2,500; the boom truck is the middle of $900 to $1,400. A: $33,600 + $42,500 + $6,720 + $1,150 = $83,970. B: $81,000 + $3,300 + $1,150 = $85,450. C: $96,000.

A went from cheapest by $47,400 to $1,480 under B. And A has the widest swing: at the ends of the lumber range it is $66,470 or $101,470. Until A’s lumber has a real takeoff and a yard price, A is a guess.

C is $10,550 over B, but C includes the wraps, setting the windows and the dumpster, which we could not price from published sources. Ask A and B to price those three in writing. If B comes in under $96,000 with them, B is your framer, subject to the paper on the hiring page.

Rural lots add a line nobody writes down: can the truss truck and the boom truck get to the house? On Georgian Bay lots, that is the site work GeorgianBaySiteworks.ca does.

Reading the Grid

  1. Send everyone the same package: plans by date, truss layout, floor system, beam list.
  2. Write the level in the first row. If two quotes are at different levels, stop and bring them up to the same one before anything else.
  3. Put the same allowance in every column. Use the middle of the range, and say so.
  4. Look at the engineering line. Trusses need sealed shop drawings and beams need sizing; someone has to supply them, and a quote that never mentions them is not cheaper, it is earlier.
  5. A blank counts as zero. If it is not written, assume it is not in the price.

The same grid works on building system packages. For a SIP, log, timber frame or modular quote, line 1 does most of the work: what level is it, and what is it missing to reach Level 4?

The Grid Is Free; the Review Is $99

Most of the time the grid answers it with a pencil and a coffee. The $99 review is for the rest: two quotes a few thousand apart with different wording, a building system package next to a framing quote, or a line you cannot tell is in or out. I read up to three framing, structural, SIP, log, timber frame or modular quotes, put them on the grid at the same level, and write down what each one left out and what I would ask. I build ICF houses, and I say so; the review reads every system on the same terms. We do not sell framers, we do not send your plans to suppliers, and we take no referral fees.

Questions people ask

Why are framing quotes for the same house so different?

Because they rarely cover the same job. One is labour only, one includes the lumber and trusses, one includes the crane and the windows. Published figures run from about $11 to $60 a sq ft for labour and materials. Bring them to the same level and the same scope first.

What should a framing quote include?

The level of completion, the measured area, the lumber package, trusses, engineered floor, beams, sheathing, wraps, whether windows are set, the crane, engineering, who handles the permit and inspection, and cleanup.

Can I compare a SIP package price with a framing quote?

Not directly. A SIP package is usually Level 1, panels delivered, with no assembly and no foundation. A framing quote is Level 2, an installed structure. Bring both to Level 4, the finished house, before you compare.

Is the cheapest framing quote a bad sign?

Usually it is an incomplete one. Price the missing lines with the same allowances and compare again. If it is still cheapest and the paper checks out, take it.

Bring every quote to the same house

The building system comparison calculator puts the same house as wood frame, SIP, ICF, log, timber frame and modular, all at Level 4, with sourced ranges, so you can see which quotes are even in the right neighbourhood. If the grid still leaves a question, the $99 review reads up to three quotes and writes down what each is missing.