How to Hire a Framer in Ontario: A Voluntary Trade, WSIB Clearance, Insurance, Working at Heights, Who Buys the Lumber, Per Square Foot vs Footprint vs Hourly, Deposits and Holdback
Hiring a Framer: Anybody Can Frame a House in Ontario, So Check Everything Else
Here is the part that surprises people. Framing is not a licensed trade in Ontario. General Carpenter is a voluntary trade, and anyone can legally frame a house. That puts the whole job of checking on you: the insurance, the WSIB, the safety training, the written scope and how the money gets paid. This page covers who you are hiring, the paper, the rates, the lumber and the money.
Framing Is a Voluntary Trade
General Carpenter is a non-compulsory trade in Ontario. The apprenticeship is about 7,200 hours, roughly four years: 6,480 on the job and 720 in school, and it is a Red Seal trade. A Certificate of Qualification tells you somebody finished that training and passed the exam. It is a quality signal, not a legal requirement, and plenty of very good framers never wrote it.
| Who shows up | May frame for pay? | What it tells you |
|---|---|---|
| General Carpenter with a Certificate of Qualification | Yes | Finished the four-year apprenticeship; Red Seal |
| Registered apprentice | Yes | Learning the trade; ask who is running the crew |
| Framer with no certificate and 20 years of houses | Yes | Legal; judge by the houses, the references and the paper below |
| You, on your own house | Yes | Permit and inspections still apply |
So “is he licensed?” is the wrong question. The right ones are: has he framed houses like mine, can I go look at one, is he covered, and will he put the scope in writing. If you are building the house yourself, the owner-builder page covers what changes when you are the general contractor, including the missing Tarion warranty.
The Paper to Ask For
Since there is no licence to look up, the paperwork carries the weight.
- A WSIB clearance certificate, current. WSIB coverage is mandatory in construction, and that includes independent operators and sole proprietors. The one-man framer with his brother-in-law on weekends is not exempt. A clearance certificate shows the account is in good standing; you can check it yourself on WSIB’s clearance page.
- A certificate of liability insurance dated past the end of your job, naming you.
- Working at Heights training for anyone using fall protection on your roof. It has to come from a CPO-approved provider and is valid for three years, so look at the date on the card.
- Two addresses of houses he framed in the last couple of years. Drive by.
On the houses we build, the walls are ICF, but the floors, interior walls and roofs are framed in wood: engineered I-joist floors bearing on the ICF walls, trusses set on top of them, stud walls on the slab. So we work with framers on every house, and the paper above is what any homeowner should ask for.
What Framers Charge in 2026
| How it is priced | Range, before HST | Source and level |
|---|---|---|
| Labour only, per sq ft of floor area | $9 to $16, and $15 to $20 | a GTA framing contractor, which gives both on one page; Level 2 |
| Labour only, per sq ft of footprint | $16 to $25+ | an Ontario framing contractor; Level 2 |
| Journeyman framer, hourly | $50 to $80 | a GTA framing contractor |
| Labour only, our planning number | $14 per sq ft of floor | inside the GTA range; Level 2 |
| Labour and materials, per sq ft | $15 to $25; $11 to $30; $30 to $60 | an estimating firm, a proptech blog, a finance guide; Level 2 |
| Labour and materials, our planning number | $40 per sq ft of floor | ordinary house with trusses; Level 2 |
October 2026 prices. Level 2 means an installed structure: framed and sheathed, not closed in, no windows, no roofing. A framing quote is never a house price; the house framing cost page works three houses through in full.
Floor Area, Footprint or the Clock
Take a two-storey house, 1,200 sq ft footprint, 2,400 sq ft of floor. At our $14 planning number per floor foot, labour is 2,400 x $14 = $33,600. A footprint price reads differently. The Ontario contractor quotes $16 to $25 or more per sq ft of footprint and does not say how a second storey changes that, so do not scale it yourself; ask. The arithmetic to keep in mind: for the same total money, a per-footprint rate on a two-storey house reads about twice a per-floor-area rate. Our $33,600 is $14 a floor foot but $33,600 / 1,200 = $28 a footprint foot. A footprint number is not cheaper or dearer than a floor number until you know which square feet it counts and what it includes.
A crew of three at $65 an hour, the middle of the journeyman range, for an 8-hour day is 3 x 8 x $65 = $1,560. The $33,600 house is about 21 or 22 of those days. Nobody frames a whole house on the clock; the slow crew would get paid more.
Ask every framer one question: which square feet? Does it count the basement, the garage, the open-to-below over the great room, the porch roof?
Who Buys the Lumber
Labour only means you, or your builder, order the lumber package, the trusses and the engineered floor, and the framer turns it into a house. Labour and materials means the framer buys it, marks it up a little and carries the risk of the takeoff being short. A Canadian finance guide puts a lumber package at $25,000 to $60,000, house size not stated.
Lumber also moves on its own. An estimating firm had commodity 2×6 SPF at about $520 per thousand board feet early in 2026 and $630 to $640 in late July, a one-year high. That is about 21 to 23 percent. If a whole $40,000 package moved with it, which not every item does, it would be about $48,500 to $49,200. Ask how long the lumber price holds and what happens after.
- Who orders, who takes delivery, and who counts it off the truck.
- Who orders the trusses. The truss plant supplies shop drawings sealed by a Professional Engineer; the roof truss page covers what the truss quote should say.
- Whether sheathing, house wrap, the crane and the dumpster are in or “by others”.
Deposits, Stage Payments, Holdback and Red Flags
A deposit that covers material ordered for your job is normal. A big deposit on a labour-only job, where there is no material to order, is not. Tie the stages to work you can see and to the framing inspection. On the $33,600 labour-only house, a split of 30, 30, 25 and 15 percent for floor decks, walls, roof sheathed and framing inspection passed is $10,080, $10,080, $8,400 and $5,040, which adds to $33,600.
On contracts the Construction Act covers, you keep a 10 percent holdback until the lien period runs out: $3,360 here, so the four cheques are $9,072, $9,072, $7,560 and $4,536, which is $30,240, and $30,240 + $3,360 = $33,600. Ask your lawyer about the timing.
A good framer asks you questions too: where the braced wall panels are on the drawings (the new rules are on the wall bracing page), where the plumbing stacks and ducts run so he does not block them, who orders the beams, and when the truss truck is coming.
- No WSIB clearance, no insurance certificate. End of conversation.
- “Cash, and you won’t need a permit.” A new house or a structural change needs one, and the inspector is the only independent eyes on the frame.
- “I’ll just cut that truss.” Nobody cuts, notches or drills a truss or an engineered joist except as the manufacturer allows.
- A price per sq ft with no area written down. See above.
One honest note: we do not run a network of framers and take no referral fees. Leads come to our office and we sort them out; outside our area we tell you straight whether we know anyone. Once quotes are in, put them through the quote comparison grid, and keep the framing inspection checklist for later.
Questions people ask
Does a framer need a licence in Ontario?
No. General Carpenter is a voluntary trade, so anyone can legally frame. A Certificate of Qualification is a quality signal. What you should require is a WSIB clearance certificate, liability insurance, Working at Heights training for roof work and a written scope.
How much does a framer charge per square foot in Ontario?
For labour only, published figures run about $9 to $20 a sq ft of floor area in the GTA, or $16 to $25 or more per sq ft of footprint. Our planning number is $14 a floor foot for labour only and $40 for labour and materials, October 2026, before HST.
Does a sole proprietor framer need WSIB?
Yes. WSIB coverage is mandatory in construction, including independent operators and sole proprietors. Ask for a current clearance certificate.
Should the framer supply the lumber?
Either works if the quote says which. Labour and materials puts the takeoff risk on the framer; labour only puts it on you. Ask how long the lumber price holds.
How much should I hold back from the framer?
On contracts the Construction Act covers, 10 percent until the lien period runs out. Tie the rest to the framing inspection.
Know the number before the first framer walks the lot
The house framing calculator prices labour only or labour and materials by floor area and shape, with a truss package and a crane day, so you know roughly where the quotes should land. If they are already in, the $99 review reads up to three of them and tells you what each one left out.
Sources and further reading
- Skilled Trades Ontario: General Carpenter: a voluntary trade in Ontario, the apprenticeship hours and the Red Seal.
- WSIB: mandatory coverage in construction: why independent operators and sole proprietors in construction must carry WSIB coverage.
- Construction Act, R.S.O. 1990: the 10 percent holdback, the lien period and the prompt-payment timelines that apply to a framing contract.