7 Ways to Get Cheap Financing for Your New Home

Construction Financing in Ontario: Progress Draw Mortgages, Cash Flow and Cost Overruns
Financing a custom home is not the same as obtaining a mortgage on a completed house. The lender releases money in stages, while the owner must keep the site moving, pay invoices on time and survive the gaps between construction spending and mortgage draws.
A construction mortgage is funded differently
Mortgage on a completed home
The lender normally advances the mortgage at closing after confirming the completed property’s value, title, insurance and borrower qualification.
The house already exists. The lender is not relying on future construction to create the collateral.
Progress-draw construction mortgage
The lender approves a maximum facility but releases money through multiple advances as the home reaches defined construction stages and passes inspections.
The owner must finance work before a draw, manage inspections and keep enough liquidity to avoid stopping the project.
How the money may move through the build
A lender does not normally reimburse every invoice as it arrives. It values completed work at agreed milestones. This example is intended to show the logic, not to predict any lender’s exact draw percentages.
| Possible stage | What may need to be complete | Cash-flow danger |
|---|---|---|
| Land / initial advance | Approved land purchase or verified equity, registered mortgage, insurance and lender conditions. | The lender may not release enough to cover all design, permit, deposit and mobilization costs. |
| Foundation draw | Excavation, footings, foundation, waterproofing, drainage and sometimes backfill, depending on the commitment. | Site work, rock, dewatering, concrete and deposits may be paid before the first construction draw. |
| Enclosed shell draw | Framing or structural walls, roof, windows and exterior doors. | Large material deposits and trade invoices can exceed the net draw after holdbacks and prior advances. |
| Mechanical / exterior draw | Plumbing, electrical, HVAC, insulation, cladding or other lender-defined work. | Many expensive systems overlap, while lender value may lag behind invoices already due. |
| Final draw | Required completion, final inspection, occupancy documentation, insurance and acceptable title/lien status. | Deficiencies, landscaping, seasonal work or missing documents can delay final funds. |
Finance the project before the project finances you
-
Establish personal borrowing capacity
Obtain a meaningful preapproval or financing review based on income, assets, debt, credit and available equity. A preapproval is not a guarantee, and the final decision also depends on the land, plans, cost and completed value.
-
Build the complete project budget
Include land, legal closing, design, engineering, permits, development charges, site work, well, septic, hydro, house construction, HST, interest, lender fees, temporary accommodation, landscaping and contingency.
-
Prepare lender-ready plans and specifications
The appraiser and lender need enough detail to understand what will be built. Incomplete plans, unrealistic allowances and missing site costs weaken both valuation and approval.
-
Match the building contract to the draw schedule
The contractor’s payment schedule and the lender’s draw schedule must be compared line by line. A mortgage approval can still fail as a construction plan if the builder is owed money weeks before the lender will release it.
-
Confirm all conditions in writing
Clarify equity requirements, first draw timing, inspection fees, interest calculation, holdbacks, cost-overrun rules, change orders, owner-builder restrictions, deadline extensions and final conversion.
-
Maintain a live cost-to-complete report
After every draw, track the original budget, approved changes, paid amounts, unpaid commitments, remaining mortgage funds and realistic cost to complete. Do not rely only on the bank balance.
Your approval is about the borrower and the build
Borrower information
- Income and employment or self-employment documents
- Credit history and current debts
- Available cash, investments and other assets
- Down payment and closing-cost evidence
- Existing mortgage and property obligations
Land and title information
- Purchase agreement or proof of ownership
- Existing debt registered against the property
- Survey, easements and access information where required
- Property taxes and insurance
- Appraised land and completed-home value
Project documents
- Complete plans and specifications
- Detailed construction budget and allowances
- Building contract and payment schedule
- Permit status and required approvals
- Construction schedule and completion target
Builder and risk information
- Builder experience, insurance and registration where applicable
- Trade quotations and major supplier commitments
- Contingency and cost-overrun capacity
- Course-of-construction insurance
- Owner-builder capability when no general contractor is used
The expenses that create financing trouble
Before the first draw
Land deposit and closing, legal work, survey, design, engineering, permits, conservation or planning reports, utility applications, builder deposits and early site investigation.
Between draws
Invoices become due before inspection, valuation and lender processing. You may need to bridge payroll, concrete, windows, mechanical equipment and other large commitments.
Costs outside the lender budget
Upgrades, landscaping, furniture, owner changes, temporary housing, storage, moving, delayed occupancy and items the appraisal does not fully recognize.
Interest and fees
Construction-period interest, appraisal or inspection charges, legal fees, lender fees, extension charges and the cost of temporary credit used to bridge draws.
Statutory holdback
Ontario’s Construction Act generally requires a 10% basic holdback. A lender may also retain or administer funds in a way that affects the net amount available to pay invoices.
Contingency and overruns
Rock, groundwater, unsuitable soil, winter work, price changes, design development, missed scope and owner changes can create costs that are not automatically added to the mortgage.
Estimate the funding gap before you sign
This calculator does not determine mortgage eligibility. It simply compares the full project funding requirement with the mortgage advances, cash and land equity you expect to have available.
Land equity is not cash and may only be recognized at the lender’s appraised value and under its lending rules. The calculator also does not model when each draw arrives. A project can have no overall funding gap and still run out of working cash between draws.
Owning the lot helps, but it does not pay invoices by itself
Land equity is the difference between the lender-accepted value of the property and debt secured against it. A lender may use verified equity as part of your required contribution, but the treatment varies.
Questions to settle
- What value will the lender use for the land?
- Will purchase price or current appraisal control?
- How will an existing land mortgage be paid out?
- How much land equity counts toward the required contribution?
- Can any cash be advanced against the lot before construction?
The common misunderstanding
A borrower may own a valuable lot and still lack enough liquid cash to reach the first construction draw. The lender’s equity calculation strengthens the loan, but trades and suppliers still expect payment in money.
The project-delivery method affects financing
| Approach | Possible lender comfort | Borrower risk |
|---|---|---|
| Fixed-price general contract | A complete contract with an experienced builder may give the lender clearer cost, schedule and responsibility. | Allowances, exclusions, escalation clauses and changes can still move the final price. |
| Cost-plus contract | The lender may require a detailed estimate, fee structure, contingency and cost-control reporting. | The owner carries more price risk because final cost is not fixed. |
| Construction management | Acceptance depends on the manager, contract structure, trade commitments and borrower experience. | Trade contracts, deposits and timing may not align neatly with lender milestones. |
| Owner-builder | Some lenders will consider it; others will not. More equity and documentation may be required. | The borrower controls procurement, scheduling, safety, insurance, payments and completion risk. |
Do not confuse the mortgage draw with the amount available to pay
Ontario’s Construction Act generally requires each payer under a construction contract or subcontract where a lien may arise to retain a basic holdback equal to 10% of the price of services or materials supplied until the applicable lien rights expire or are otherwise satisfied, discharged or provided for.
Why this matters to financing
A progress inspection may support a draw based on completed value, but statutory or lender holdbacks can reduce the net funds available. The builder’s invoice and the lender’s net advance may therefore be different.
What to coordinate
The construction contract, lender, lawyer and payment administrator should use one clear procedure for invoices, holdbacks, statutory declarations, lien searches and releases.
A rebate can improve the final economics without solving the draw gap
Owner-built and builder-purchased homes may qualify for different federal and Ontario housing rebates when the legal requirements are met. In 2026, the federal first-time home buyers’ GST/HST rebate can provide eligible buyers up to $50,000, and Ontario introduced a temporary enhanced rebate applying to qualifying builder-purchased homes and owner-built homes where construction begins within the specified 2026-2027 window.
Keep the paper trail
CRA guidance requires original invoices and supporting records. Quotes, credit-card slips and bank statements do not replace acceptable invoices. Keep contracts, change orders, proof of payment and occupancy records organized throughout construction.
Confirm the claimant and structure
Eligibility can depend on who owns the land, who paid the invoices, intended occupancy, construction dates, fair market value and whether the applicant is treated as a builder for GST/HST purposes.
Get these answers before signing the building contract
Approval and equity
- What borrower contribution is required?
- How is land equity valued and credited?
- What costs are excluded from the mortgage?
- What completed value is required?
- What happens if the appraisal is lower than expected?
Draw administration
- How many draws are allowed?
- What exact milestone triggers each draw?
- Who orders and pays for inspections?
- How long after inspection are funds released?
- How are holdbacks deducted and released?
Budget changes
- Can the mortgage increase after approval?
- How are change orders reported?
- What contingency must remain unused?
- Can savings in one category cover another?
- What happens if the project is over budget?
Time and completion
- When must the first draw occur?
- How long may construction take?
- What extension fees or reapproval are possible?
- What is required for the final draw?
- How and when does the loan convert to a regular mortgage?
Build the budget before asking the lender to finance it
Ontario Custom Home Building Calculator
Estimate the house, site work, permits, professional fees, utilities, contingencies and other major project categories.
Build My Project BudgetOntario Lot-Buying Bible
Review servicing, zoning, access, site costs, financing and the complete go/no-go decision before buying the property.
Get the Lot BibleOntario Building Permit Bible
Organize consultants, drawings, submission requirements, fees and inspections in the order the project needs them.
Get the Permit BibleContinue planning the complete project
Sources used for this guide
- Financial Consumer Agency of Canada: mortgage preapproval
- Financial Consumer Agency of Canada: mortgage qualification and stress test
- RBC: construction mortgages and example progress draws
- Scotiabank: progress-draw construction mortgage description
- Ontario Construction Act
- CRA: GST/HST new housing rebates
- CRA: Ontario enhanced new housing rebate
- FSRA: working with an Ontario mortgage professional
Last reviewed: July 25, 2026. Lender programs, underwriting policies, interest rates and government rebates can change. Confirm current terms directly with the lender, mortgage professional, lawyer and tax adviser handling your project.
Construction financing in Ontario
What is a construction mortgage in Ontario?
A construction mortgage finances a home that is being built rather than a completed house. Instead of advancing the full mortgage at closing, the lender normally releases funds in progress draws after specified construction milestones are completed and inspected.
How do progress draws work on a custom home?
The lender approves a maximum mortgage, then advances portions as the project reaches lender-defined stages. Typical stages may include land or start-up funding, foundation, enclosed framing, mechanical and exterior completion, and final completion. The exact number, timing and percentage of draws vary by lender.
Do I need cash before the first construction draw?
Usually, yes. Many borrowers must pay for land closing, design, engineering, permits, deposits, excavation or other early work before enough progress exists for a lender draw. Confirm the first eligible draw milestone and prepare a written cash-flow plan before construction begins.
Can land equity be used toward a construction mortgage?
A lender may recognize some verified equity in land you already own, but the amount and how it is credited depend on the lender’s appraisal, title position, existing debt and lending policy. Do not treat the full market value of the lot as available cash until the lender confirms it in writing.
How much contingency should I carry when building a house?
There is no universal percentage, but a realistic construction budget needs a separate contingency for unknown site conditions, price changes, design revisions and owner changes. Many planning budgets use at least 10 percent, while difficult rural or waterfront projects may require more.
Does the lender pay the builder directly?
That depends on the mortgage and legal arrangement. Some lenders advance funds to the borrower or lawyer after an inspection, and the borrower then pays the builder according to the construction contract. The draw process, required invoices, statutory declarations and payment direction should be confirmed before signing.
What is the Ontario construction lien holdback?
Ontario’s Construction Act generally requires a payer under a construction contract or subcontract to retain a basic holdback equal to 10 percent of the price of services or materials supplied until the applicable lien rights have expired or otherwise been dealt with. Obtain legal advice for the payment and release process on your project.
Can an owner-builder get construction financing?
Some lenders finance owner-builder projects and others do not. Where permitted, the lender may require more equity, detailed cost estimates, trade quotations, permits, insurance, a qualified project manager and stronger proof that the borrower can complete the home within the approved budget and schedule.
Should I count an HST rebate as construction cash?
Do not spend a projected rebate before confirming eligibility and timing. Rebate programs can be substantial, but owner-built claims are generally filed after the required construction or occupancy milestone and may be processed later. Keep original invoices and plan the project so it can finish without relying on rebate money arriving early.
When does a construction mortgage become a regular mortgage?
After the lender’s final requirements are satisfied, which may include substantial or full completion, a final inspection, occupancy documentation, insurance and confirmation that title and lien issues are acceptable, the construction facility is normally converted or renewed into a conventional mortgage with regular principal-and-interest payments.
Building in Simcoe County or Georgian Bay?
BuildersOntario teaches across Ontario. ICFhome builds in our local construction area. Harvey Juric and the ICFhome team have built more than 300 custom homes, including more than 250 ICF homes.
Service area: Collingwood, Wasaga Beach, Blue Mountains, Stayner, Barrie, Springwater, Oro-Medonte, Midland, Penetanguishene, Tiny and Tay; occasionally beyond for challenging projects or where the client lacks a contractor.
Important: This page provides general educational information, not mortgage, legal, accounting, tax or investment advice. Construction financing is lender-specific and property-specific. Obtain written commitments and independent professional advice before entering contracts or relying on projected advances or rebates.