A vanity install is a plumber’s job that a carpenter gets dragged into, or the other way round, and the price depends on which of them has to do the thing they did not expect. Here is what each trade charges, what is in the quote, and why the same vanity costs $400 to install in one house and $1,500 in the one next door.
The numbers
| Job | Labour | Time | Who |
|---|---|---|---|
| Straight swap: same size, same drain and supply location, top and sink pre-assembled | $350 to $600 | 2 to 3 hours | Plumber, or a handyman plus a plumber for the connections |
| Swap with a separate top: set the vanity, set the top, mount an undermount sink, drill the faucet holes | $500 to $900 | 3 to 5 hours | Carpenter or installer, then plumber |
| Wider vanity, drain and supplies have to shift 6 to 12 in. inside the wall | $900 to $1,500 | Half a day to a day | Plumber, drywall patch by others |
| Double vanity replacing a single: second drain, second supply pair, wall opened | $1,200 to $2,000 | 1 to 2 days | Plumber, drywaller, painter |
| Floating (wall-hung) vanity, blocking added in the wall | $700 to $1,400 | Half a day, plus the wall | Carpenter for the blocking, plumber for the rough-in |
| Remove and dispose of the old vanity | $100 to $250 | Under an hour | Whoever is there first |
The vanity calculator adds the right line from this table to the price of whatever vanity you pick.
Who does what
A plumber in Ontario charges $110 to $170 an hour, with a one or two hour minimum, and does the part that matters: the shut-offs, the P-trap, the supply lines, the faucet and the drain assembly, the test for leaks. A carpenter, installer or handyman charges $65 to $110 an hour and does the part that takes longest: levelling the cabinet on an uneven floor, scribing the filler to a wall that is not plumb, securing the cabinet to the studs, setting the top, cutting the back of the cabinet for the pipes, and the trim. On a straight swap one person often does both and does not mind. On anything where the wall gets opened, it is two trades and you should expect two invoices, or one contractor who bills for both.
What is in a proper install quote
- Shut off and disconnect the old faucet, trap and supplies.
- Remove the old vanity and top; cap or protect the stub-outs.
- Check the floor for level and the wall for plumb; shim the new cabinet level and plumb; scribe a filler or the side if the wall is out.
- Cut the cabinet back or floor for the drain and supplies.
- Secure the cabinet to the wall studs with screws through the hanging rail (not into drywall).
- Set the top in silicone; mount an undermount sink with clips and silicone if the top did not come with it fitted.
- Install the faucet, drain assembly, pop-up, P-trap and new supply lines (new ones, every time; the old braided lines are the ones that flood bathrooms).
- Replace the shut-off valves if they are the old multi-turn type or do not fully close.
- Caulk the top to the wall and the backsplash.
- Run water, fill the basin, drain it, check every joint dry. Twice.
- Haul away the old vanity and the packaging.
What is not in it unless it says so: new shut-off valves (a $40 to $80 part each, and worth it), moving anything inside the wall, drywall repair and paint, tile repair where the old vanity was wider, the mirror and the light, and electrical. The plumbing problems page is the list of what the plumber finds when the old vanity comes out.
The five things that turn two hours into a day
- The drain is in the wrong place for the new vanity. A drawer-base vanity needs the trap to clear the drawers, which it will not if the old drain comes out of the wall at 20 in. and the new vanity’s drawers run the full depth. The options are a shallower drawer, an offset drain kit ($40 to $90, and a notched drawer), or moving the drain ($400 to $900 with the wall opened). Check the vanity’s drawings against the stub-out height before buying it; the sizes and heights page has a fit checker that asks for this.
- The new vanity is narrower than the old one. There is a stripe of unfinished floor and wall where the old one was. Tile patching, or a filler, or a wider vanity. The smarter order is to pick a vanity the same width or wider.
- The shut-offs do not shut off. Every plumber has a story. Old multi-turn valves seize or weep, and the fix is new quarter-turn valves, which means draining the house line, which is the extra hour on the invoice. Budget it; it is the best $150 in the job.
- The floor is out of level or the wall is out of plumb. A 1/2 in. drop across a 36 in. vanity is normal in an older house and means shimming, a tapered toe kick, and a scribed side. A wall that leans means a filler strip or a gap at the top.
- The top does not come assembled. A big-box vanity with the sink glued in and the holes drilled is a two-hour install. A separate quartz top with an undermount sink that has to be mounted, and a faucet whose holes have to be drilled on site, adds two hours and a worry.
Floating vanities, which are their own thing
A wall-hung vanity carries its own weight and a full basin of water and a person leaning on it, all on the screws into the wall. It needs 2×6 or 3/4 in. plywood blocking between the studs at the right height, which is in the wall before the drywall in a new bathroom and is a hole in the drywall in an old one. The plumbing also has to come out of the wall at the vanity’s height, not the floor, because there is no cabinet to hide a floor drain in. The install itself is quick once the blocking is in; the blocking is the cost. The floating vs. freestanding page goes through whether it is worth it.
Doing it yourself
A straight swap of a pre-assembled vanity, with the stub-outs where they were, working shut-offs and a level floor, is a reasonable Saturday for someone who owns a level, a drill and an adjustable wrench, and the plumbing supply store will sell you the trap kit and the new supplies for $60. The parts that go wrong for first-timers: over-tightening the compression fittings (snug plus a quarter turn, not more), not replacing the supply lines, the pop-up drain assembly (follow the faucet’s instructions exactly, and use plumber’s putty or the gasket it came with, not both), and finding the shut-offs do not close. If any of the five things above is true of your bathroom, it is a plumber’s job and the $500 is well spent.
Questions people ask
How much does a plumber charge to install a bathroom vanity?
$350 to $600 for a straight swap in Ontario, at $110 to $170 an hour with a minimum. $900 to $2,000 when the drain or supplies move or a second sink is added.
How long does it take to install a bathroom vanity?
Two to three hours for a swap with a pre-assembled top. Half a day with a separate top and undermount sink. A day or two when the wall is opened.
Do I need a plumber to replace a bathroom vanity?
Not for connecting a new faucet and trap to existing stub-outs with working shut-offs. Yes for anything inside the wall: moving a drain, adding a second sink, re-venting.
Does vanity installation include the faucet?
Usually the labour to install the faucet you supply is included. The faucet itself is not, and a faucet with a separate drain assembly adds half an hour.
Should I replace the shut-off valves when replacing the vanity?
If they are the old multi-turn type, or over 15 years old, yes. $40 to $80 a valve in parts, about an hour of labour for the pair, and the only time it is cheap is while the vanity is out.
Before you buy the vanity
Measure the stub-outs, check the shut-offs, check the floor, and buy a vanity the old footprint fits inside. Then the install is the cheap line on the invoice.