Roof Underlayment and Ice and Water Shield: What the Ontario Building Code Requires, Where Good Roofers Put More, and What It Costs
What Goes Under the Shingles, Where the Code Says It Has to Go, and Where a Good Roofer Puts It Anyway
Shingles shed rain. They do not stop water that is pushed uphill by wind, or backed up behind an ice dam, or running down a valley at the speed of a creek. The layer under them does that, and it is the part of the roof you will never see and the part the cheap quote skimps. This is what it is, where the Ontario Building Code requires it, and where it should go on top of that.
The two products
Ice and water shield (eave protection)
A self-adhering sheet of rubberized asphalt on a polyethylene film, about 1 mm thick, that sticks to the deck and seals itself around every nail driven through it. Water cannot get under it and cannot get through a nail hole. Grace Ice and Water Shield, IKO ArmourGard, GAF WeatherWatch, and a dozen others. $0.60 to $1.00 a square foot installed on top of the base rate when used beyond the included areas.
Underlayment
The sheet over the rest of the deck. Synthetic (a woven polypropylene, 15 to 30 mils, GAF FeltBuster, IKO Stormtite, Titan and others) has replaced felt paper on almost every roof: lighter, stronger, does not wrinkle in the rain, does not tear in wind before the shingles go on, and lasts the life of the roof. It is not self-sealing; nails through it are sealed by the shingle above. Included in every installed rate on this site.
What the Ontario Building Code requires
The Code requires eave protection on shingle, shake and tile roofs: a membrane at the eaves extending from the edge of the roof at least 900 mm (about 3 ft) up the slope, and to a line at least 300 mm (about 1 ft) inside the inner face of the exterior wall. On a house with a 2 ft overhang and a 2×6 wall, that is about 3 ft of eave protection measured along the slope, more on a low pitch where 300 mm inside the wall is further up the roof. There are exemptions: roofs over unheated garages, carports and porches; roofs steeper than 1 in 1.5 (about 8/12, where water runs off before it can back up); and a few others that a roofer will know. Check the current edition for your municipality, but in practice every Ontario roofer runs a 3 ft (one roll width) or 6 ft (two) band of ice and water at every eave and does not argue about it.
Where a good roofer puts it anyway
- Valleys. A 3 ft strip centred on every valley, under the metal or under the woven shingles. Valleys carry the water of two roof planes and are where wind-driven rain goes uphill.
- Around everything that pokes through. Chimneys, skylights, plumbing stacks, vents: a square of membrane under the flashing, lapped so water runs onto, not under, the membrane below.
- Along walls. Where the roof meets a sidewall or a dormer, a strip turned up the wall behind the step flashing.
- Rakes. The gable edges, in windy sites; not required, but it is $30 a roll.
- Low slopes. From 2/12 to 4/12, where shingles are marginal, full coverage of the whole deck is cheap insurance and what most manufacturers require for their warranty.
- North-facing cottage roofs, and any roof that has had an ice dam. Full coverage. The dam will come back (the fix for that is in the attic, on the ice dam page), and full coverage means the backed-up water cannot get into the house while you fix the cause.
The order it goes on, which is where mistakes are made
- Drip edge at the eaves, nailed to the deck, first.
- Ice and water shield at the eaves, over the drip edge, so water on the membrane runs onto the metal and off.
- Ice and water in the valleys and around penetrations.
- Synthetic underlayment over the rest, lapped over the top edge of the eave membrane, each course lapping the one below by the manufacturer’s line, cap-nailed.
- Drip edge at the rakes, over the underlayment, so wind-driven rain at the gable runs onto the underlayment and not under it.
- Starter strip, then shingles.
Drip edge under at the eaves and over at the rakes is the detail that tells you whether the crew knows what the layers are for. Backwards, the eave membrane sheds water behind the fascia and the rakes let it under the underlayment. The installation checklist has you look at the eave edge before the shingles cover it.
Felt, if someone offers it
Fifteen-pound asphalt felt was the underlayment for a century and still works. It also wrinkles when it gets wet before the shingles go on (the wrinkles telegraph through), tears in wind, and degrades under shingles over 20 years to something you can poke a finger through. Synthetic costs a few dollars a square more and is better in every way; a quote with felt on it is a quote from a roofer who has not changed a habit, which is a small thing on its own and a reason to look at the rest of the quote.
Questions people ask
Where is ice and water shield required in Ontario?
At the eaves of shingle roofs, from the edge at least 900 mm up the slope and to 300 mm past the inside face of the exterior wall, under the Ontario Building Code, with exemptions for unheated spaces and steep roofs. Good roofers also put it in valleys and around penetrations.
Should I get ice and water shield on the whole roof?
On a low slope (under 4/12), on a roof that has had ice dams, or on a shaded north-facing cottage roof, yes. On a steep, sunny, well-vented roof it is optional; the attic ventilation matters more. About $0.85 a square foot extra.
Is synthetic underlayment better than felt?
Yes: stronger, lighter, does not wrinkle or tear, lasts the life of the roof. It costs a few dollars a square more. Felt on a 2026 quote is a habit, not a choice.
Does ice and water shield stop ice dams?
No. It stops the water behind an ice dam from getting into the house. The dam itself comes from heat leaking into the attic, and the fix is air sealing, insulation and ventilation below the roof.
How much does ice and water shield cost?
About $0.60 to $1.00 per square foot installed. A roll covers about 200 sq ft and costs $90 to $160. The code-minimum eaves and valleys are inside a normal installed rate; full coverage is the extra.
Ask where it goes
Eaves to code, valleys, penetrations, walls. Synthetic over the rest. Drip edge under at the eave, over at the rake. If the roofer can say that back to you without looking it up, the layer you will never see is going to be right.
Sources and further reading
- Ontario’s Building Code: the official page, with the current regulation (O. Reg. 163/24). Roofing is Section 9.26, attic ventilation 9.19.
- O. Reg. 163/24, the Building Code regulation: the full text if you want to read 9.26 and 9.19 yourself.
- IKO: Canadian-made shingles; the warranty and the technical data sheets are on the site.