Construction Adjudication in Ontario (ODACC): Cost, Timeline and When It’s Worth It

Ontario β€” Adjudication (ODACC)Fees as of October 1, 2026Reviewed October 2026

Adjudication: the fast lane most trades have never heard of.

A mostly paper-based process where an adjudicator decides a payment dispute about a month after your documents are in. No lawyer required. Here’s what it costs, how it works, and the claim size where it starts to make sense.

190-day window2~30-day decision3Fee split two ways4Pay within 15 days

What adjudication is β€” and why most trades have never used it

Ontario’s Construction Act set up adjudication so payment fights on a job could be decided in weeks instead of years. It’s run through ODACC, the Ontario Dispute Adjudication for Construction Contracts. You file a notice, an adjudicator is appointed, both sides send in documents, and you get a decision the other side has to pay β€” now. Either side can still take the dispute to court later, but the money moves first.

In its 2025 fiscal year ODACC saw 324 adjudications, and the median claim was about $212,800. Read that number again: this tool has mostly been used by bigger players. Small trades barely touch it, and in my experience that’s mainly because nobody ever told them it exists.

Owed money on a job? Get a builder on your side.

A builder’s handbook you can download right now, a review of your own paperwork, or a lawyer when it’s lawyer’s work. Written by an Ontario builder — not legal advice.

Instant download

The Ontario Lien Handbook

$29.99

File a lien yourself — or get one off your title.

  • Step by step: your deadline, the parcel register, the amount, the claim for lien
  • What you can do yourself and what needs a lawyer — so you pay for less of it
  • Lien on your house or job? Your real exposure, a validity checklist and 8 ways out
  • 6 letters, 4 worksheets and a numbers card to tape on the wall
35-page PDF · download right after checkout
Get the handbook — $29.99
Most complete

Builder Payment Review

$99.99

A builder goes through your own paperwork and tells you where you stand.

  • The Ontario Lien Handbook included
  • Your deadlines worked out from your own dates
  • Every document rated line by line: what you can prove and what you can’t
  • The excuse you were given, tested against what the Act requires of them
  • The amount you can defend claiming — extras, holdback, interest
  • Every route ranked by what it would net you, and a 14-day plan
  • A two-page brief a lawyer can quote from in one call
Emailed within 2 business days
Get my review — $99.99
Deadline close?

Talk to a construction lawyer

The lawyer bills you directly

When it’s lawyer’s work, go straight to a lawyer.

  • Your lien deadline is inside two weeks
  • A lien or claim has been registered against you
  • You want to go after the directors personally
  • We point you to an independent Ontario construction lawyer — and take no referral fee
Independent lawyer · billed by the lawyer, not us
Ask for a lawyer referral
✓ Written and checked by Harvey Juric, Ontario builder since 1979✓ Current to October 2026✓ Not a law firm — we tell you when you need one

What you can take to adjudication

  • Payment under the contract or subcontract β€” including approved, unapproved and proposed change orders.
  • What the work or materials were worth.
  • Amounts in a notice of non-payment.
  • Set-off claimed against you.
  • Holdback β€” including whether it should have been released.
  • Since 2026, scope, price changes and time extensions, where deciding them is needed to decide one of the above.
  • Anything else both sides agree to put to the adjudicator.

One dispute per adjudication, unless both sides agree to more. The disputed-work-now, argue-later situation β€” where you were told to do a change and fight about the price afterwards β€” is exactly what this is for.

The 90-day window

Since January 1, 2026, you can start an adjudication up to 90 days after the contract is completed, abandoned or terminated. For a sub, the 90 days run from the earliest of that date, the date your subcontract was certified complete, or your own last supply. Before 2026 you had to start before the contract was finished, which shut a lot of final-payment and holdback fights out.

The usual way to lose this route – waiting on a cheque that’s β€œcoming next week” until the 90 days are gone. Diary the date the day you finish.

What it costs β€” and when it isn’t worth it

Amount claimedAdjudicator’s fee (if the parties don’t agree one)
Under $10,000$1,600 + HST
$10,000 – $24,999$2,000 + HST
$25,000 – $34,999$3,000 + HST
$35,000 – $49,999$4,000 + HST
$50,000 – $249,999$300 an hour + HST, plus referral and certification fees

The fee is split equally unless the adjudicator orders otherwise, and each side pays its own other costs, win or lose. If the other side won’t pay its half, you may have to front it to keep things moving.

So here’s the math. On a $5,000 claim, your half of the fee comes to about $904 with HST β€” roughly 18% of the debt. If you end up fronting the whole thing, it’s about 36%. On a few thousand dollars, a demand letter or Small Claims usually nets you more. On $25,000 and up, owed by a company with money, adjudication starts to look very good indeed.

How it works, step by step

StepWhat happensTiming
1. NoticeYou file a notice of adjudication through ODACC’s online system: the parties, what the dispute is, what you want, and a proposed adjudicator. The other side gets it the same day.Day 0
2. AdjudicatorAgreed between you, or appointed by ODACC.About 4–11 days
3. Your documentsThe contract, your invoices and the documents you rely on, inside the page limits for the process chosen.Within 5 days of appointment
4. DecisionThe adjudicator decides, usually on paper.30 days after your documents, unless extended

Realistically, six to eight weeks from notice to decision. Page limits are tight β€” some processes allow only a few pages each, not counting the contract and the invoice β€” so a clean, indexed file wins.

After the decision

  • The other side has 15 days to pay (it was 10 before 2026), with interest on late amounts.
  • If they don’t pay, you can suspend work until they do, and recover your reasonable costs of stopping and restarting.
  • You can file the certified decision with the court within two years, and enforce it like a court order β€” garnishment, writs, the usual tools.
  • Appeals are hard. Judicial review needs permission from the Divisional Court, on narrow grounds, and asking for it doesn’t stop the clock on paying.
One weakness to know – adjudication has no collection arm of its own. Against a company that’s broke, a decision is worth what you can collect. That’s where trust claims come in.

Before you file on a public job

Some public owners treat an adjudication like a lawsuit under their bidding policies, and a few have been reported to keep lists of contractors who have taken them on. It shouldn’t matter, and it’s your right either way β€” but read the owner’s procurement policy before you file, so you’re not surprised.

Questions trades ask

Do I need a lawyer?

No. Lawyers are allowed but not required.

What does it cost?

Under $10,000: $1,600 + HST. $10,000–$24,999: $2,000. $25,000–$34,999: $3,000. $35,000–$49,999: $4,000. Split equally; each side pays its own other costs.

Is it worth it on a small claim?

On a few thousand dollars the fee eats a big share β€” your half on a $5,000 claim is about 18%. It makes more sense as the amount rises and the payer is solvent.

How long does it take?

Usually about six to eight weeks from notice to decision.

Is the decision final?

It's binding in the meantime β€” the other side must pay β€” but either party can take the dispute to court or arbitration later.

How long does the other side have to pay?

15 days after the determination is communicated (since 2026).

Does adjudication extend my lien deadline?

Don't count on it. The January 2026 amendments changed how adjudication and lien deadlines interact. Treat your lien deadline as running on its own and protect it separately.

Not legal advice. This is general information from an Ontario builder, current to October 2026. Your dates and rights depend on your contract and your facts β€” confirm them with an Ontario construction lawyer before you rely on them. Read the Construction Act on ontario.ca.

Ready to get paid? Pick the help that fits.

Start with the handbook — it walks you through filing a lien, or fighting one, step by step. Want a builder to go through your own paperwork? The Builder Payment Review comes back within two business days.

Instant download

The Ontario Lien Handbook

$29.99

File a lien yourself — or get one off your title.

  • Step by step: your deadline, the parcel register, the amount, the claim for lien
  • What you can do yourself and what needs a lawyer — so you pay for less of it
  • Lien on your house or job? Your real exposure, a validity checklist and 8 ways out
  • 6 letters, 4 worksheets and a numbers card to tape on the wall
35-page PDF · download right after checkout
Get the handbook — $29.99
Most complete

Builder Payment Review

$99.99

A builder goes through your own paperwork and tells you where you stand.

  • The Ontario Lien Handbook included
  • Your deadlines worked out from your own dates
  • Every document rated line by line: what you can prove and what you can’t
  • The excuse you were given, tested against what the Act requires of them
  • The amount you can defend claiming — extras, holdback, interest
  • Every route ranked by what it would net you, and a 14-day plan
  • A two-page brief a lawyer can quote from in one call
Emailed within 2 business days
Get my review — $99.99
Deadline close?

Talk to a construction lawyer

The lawyer bills you directly

When it’s lawyer’s work, go straight to a lawyer.

  • Your lien deadline is inside two weeks
  • A lien or claim has been registered against you
  • You want to go after the directors personally
  • We point you to an independent Ontario construction lawyer — and take no referral fee
Independent lawyer · billed by the lawyer, not us
Ask for a lawyer referral
✓ Written and checked by Harvey Juric, Ontario builder since 1979✓ Current to October 2026✓ Not a law firm — we tell you when you need one