Prompt Payment in Ontario: The 28-Day, 7-Day and Day-35 Rules
The owner hasnβt paid him. That doesnβt mean he doesnβt have to pay you.
Ontarioβs prompt payment rules put a hard date on every step of the payment chain. Hereβs how they work from the tradeβs side β and what a GC has to do before βthe owner hasnβt paidβ becomes a lawful reason to sit on your money.
What prompt payment is, and which jobs it covers
Since October 2019, Ontarioβs Construction Act has set deadlines for paying invoices down the chain: owner to general contractor, GC to sub, sub to sub-sub and supplier. It applies where the main contract was signed, or the procurement started, on or after October 1, 2019.
- Nobody can contract out of it. The Act applies whatever the contract says, and every contract and subcontract is treated as amended to comply.
- Home renovations arenβt exempt. Thereβs no residential carve-out in the Act β a homeowner who hires a contractor is an βowner.β
- Suppliers are covered too. A supplier hired by a contractor or a trade is treated as a subcontractor.
Owed money on a job? Get a builder on your side.
A builder’s handbook you can download right now, a review of your own paperwork, or a lawyer when it’s lawyer’s work. Written by an Ontario builder — not legal advice.
The Ontario Lien Handbook
File a lien yourself — or get one off your title.
- Step by step: your deadline, the parcel register, the amount, the claim for lien
- What you can do yourself and what needs a lawyer — so you pay for less of it
- Lien on your house or job? Your real exposure, a validity checklist and 8 ways out
- 6 letters, 4 worksheets and a numbers card to tape on the wall
Builder Payment Review
A builder goes through your own paperwork and tells you where you stand.
- The Ontario Lien Handbook included
- Your deadlines worked out from your own dates
- Every document rated line by line: what you can prove and what you can’t
- The excuse you were given, tested against what the Act requires of them
- The amount you can defend claiming — extras, holdback, interest
- Every route ranked by what it would net you, and a 14-day plan
- A two-page brief a lawyer can quote from in one call
Talk to a construction lawyer
When it’s lawyer’s work, go straight to a lawyer.
- Your lien deadline is inside two weeks
- A lien or claim has been registered against you
- You want to go after the directors personally
- We point you to an independent Ontario construction lawyer — and take no referral fee
The chain: 28 days, 7 days, day 35, day 42
| Step | The rule | The way out |
|---|---|---|
| Owner pays the GC | Within 28 days of a proper invoice | A notice of non-payment within 14 days, stating the amount withheld and every reason |
| GC pays you | Within 7 days of being paid for your work | A notice disputing your entitlement, with reasons |
| Owner didnβt pay the GC | The GC still pays you by day 35 after its own invoice to the owner | A formal notice to you, the ownerβs notice attached, and a promise to adjudicate against the owner within 21 days |
| You pay your subs and suppliers | Within 7 days of being paid; backstop at day 42 | The same kind of notice, passed down |
Is my invoice to the GC a βproper invoiceβ?
No. The proper-invoice rules apply between the owner and the GC. Your clock runs off the GCβs invoice to the owner and the date the GC gets paid β which is why the next section matters.
What is a βproper invoiceβ?
A GCβs invoice to the owner with the details the Act requires: who itβs from, the date and the period or milestone it covers, the contract or PO it relates to, a description of the work, the amount and payment terms, and who to pay. Since January 2026, if the owner doesnβt object in writing within 7 days, the invoice is treated as proper β the owner canβt dig up a technicality a month later.
βThe owner hasnβt paid meβ β what the GC actually has to do
This is the line every trade has heard. Hereβs the rule. If the owner didnβt pay, the GC can only hold your money past day 35 if it does three things on time:
- Gives you a written notice of non-payment in the prescribed form,
- attaches the ownerβs own notice of non-payment, and
- commits to start adjudication against the owner within 21 days.
No paperwork, no excuse: the full amount is due by day 35, plus interest. Pay-when-paid clauses in the subcontract arenβt banned, but they only protect a GC who follows this procedure.
Find out when the GC invoiced the owner
Every date below you runs from the day the GC gave the owner its proper invoice. Youβre entitled to ask, and the GC has to tell you. Do it in writing:
βPlease confirm the date you gave the owner your proper invoice that included our work for [period / invoice number].β
Then count. Day 35 from that date is when your money is due if the owner hasnβt paid and you havenβt received a proper notice.
Invoice so the clock works for you
- Bill monthly unless your contract says otherwise. Thatβs the Actβs default rhythm, and it keeps your work in the GCβs monthly invoice to the owner.
- Never save changes for the final invoice. Surprise extras on the last bill invite a fight and hold up the whole payment. Bill approved changes in the month you do them.
- βThe architect hasnβt certified it yetβ doesnβt stop the ownerβs clock. A proper invoice canβt be made to depend on certification or owner approval, except for testing and commissioning.
- Re-sending an invoice resets nothing. A revised invoice keeps its original date. So when they say βsend it again,β send it β and keep proof of when you sent the first one.
When they withhold: notices of non-payment and set-off
A payer who disputes your invoice has to say so in a notice of non-payment, on time, with the amount and every reason. Reasons that appear for the first time after you ask for your money β a list of complaints nobody mentioned while you were working β are worth testing at adjudication.
And if the GC simply left your work off its invoice to the owner, so the owner never paid for it, you can take that straight to adjudication against the GC.
Interest on late money
Late amounts carry interest at the court prejudgment rate β 2.5% through 2026 β or your contract rate if itβs higher. At 2.5%, paying late costs the payer almost nothing, so put a proper rate in your contract.
Can I stop work?
Under the Act, you get a right to suspend work when an adjudicatorβs decision goes unpaid past its 15-day deadline β and you can recover your reasonable costs of stopping and restarting. Outside that, it depends on your contract.
Walking off without a right to can be treated as abandoning the job, and suddenly youβre the one being sued. If youβre thinking about stopping, talk to a lawyer first, and put everything in writing.
Questions trades ask
How fast must the owner pay the GC?
Within 28 days of a proper invoice, unless the owner gives a notice of non-payment within 14 days stating the amount withheld and every reason.
How fast must the GC pay me?
Within 7 days of being paid by the owner for your work.
What if the owner hasn't paid the GC?
The GC must still pay you by day 35 after its invoice to the owner β unless it gives you a formal notice (Form 1.2) with the owner's notice attached and undertakes to start adjudication against the owner within 21 days.
Are pay-when-paid clauses legal?
They aren't banned, but they protect the GC only if it follows the statutory notice-and-adjudicate procedure. Otherwise the day-35 rule applies.
Does prompt payment apply to home renovations?
There is no residential exemption in the Act; a homeowner who hires a contractor is an "owner." Confirm on your facts.
Do I get interest on late payments?
Yes β at the court prejudgment rate (2.5% through 2026) or your contract rate if higher. State any contract rate as a yearly rate.
Can I stop work if I'm not paid?
Under the Act, only after an adjudication determination goes unpaid. Otherwise it depends on your contract β walking off without a right risks being treated as abandonment.
Not legal advice. This is general information from an Ontario builder, current to October 2026. Your dates and rights depend on your contract and your facts β confirm them with an Ontario construction lawyer before you rely on them. Read the Construction Act on ontario.ca.
Getting paid: the full set of guides
Ready to get paid? Pick the help that fits.
Start with the handbook — it walks you through filing a lien, or fighting one, step by step. Want a builder to go through your own paperwork? The Builder Payment Review comes back within two business days.
The Ontario Lien Handbook
File a lien yourself — or get one off your title.
- Step by step: your deadline, the parcel register, the amount, the claim for lien
- What you can do yourself and what needs a lawyer — so you pay for less of it
- Lien on your house or job? Your real exposure, a validity checklist and 8 ways out
- 6 letters, 4 worksheets and a numbers card to tape on the wall
Builder Payment Review
A builder goes through your own paperwork and tells you where you stand.
- The Ontario Lien Handbook included
- Your deadlines worked out from your own dates
- Every document rated line by line: what you can prove and what you can’t
- The excuse you were given, tested against what the Act requires of them
- The amount you can defend claiming — extras, holdback, interest
- Every route ranked by what it would net you, and a 14-day plan
- A two-page brief a lawyer can quote from in one call
Talk to a construction lawyer
When it’s lawyer’s work, go straight to a lawyer.
- Your lien deadline is inside two weeks
- A lien or claim has been registered against you
- You want to go after the directors personally
- We point you to an independent Ontario construction lawyer — and take no referral fee
More from BuildersOntario – scroll to explore.