How to Register a Construction Lien in Ontario

Register it right. Register it on time.
You did the work, supplied the materials, and then the payment vanished like a sock in the laundry. A lien ties your unpaid claim to the property you improved. The right is automatic — keeping it alive means hitting two strict deadlines and getting the details exactly right. Here’s the plain-English version.
What a construction lien actually does
A construction lien is a claim registered against the title of a property by someone who supplied labour or materials to improve it and wasn’t paid. It secures your claim against the land itself. In plain terms, your lien says: “I improved this property, and I have a claim on it until I’m paid.” Owners can’t easily sell or refinance with one on title, which is exactly why liens get cheques written.
Not sure a lien is your best move? Start with what to do when you’re not paid — it compares every route by what ends up in your pocket. Already past the deadline? See missed the lien deadline.
Owed money on a job? Get a builder on your side.
A builder’s handbook you can download right now, a review of your own paperwork, or a lawyer when it’s lawyer’s work. Written by an Ontario builder — not legal advice.
The Ontario Lien Handbook
File a lien yourself — or get one off your title.
- Step by step: your deadline, the parcel register, the amount, the claim for lien
- What you can do yourself and what needs a lawyer — so you pay for less of it
- Lien on your house or job? Your real exposure, a validity checklist and 8 ways out
- 6 letters, 4 worksheets and a numbers card to tape on the wall
Builder Payment Review
A builder goes through your own paperwork and tells you where you stand.
- The Ontario Lien Handbook included
- Your deadlines worked out from your own dates
- Every document rated line by line: what you can prove and what you can’t
- The excuse you were given, tested against what the Act requires of them
- The amount you can defend claiming — extras, holdback, interest
- Every route ranked by what it would net you, and a 14-day plan
- A two-page brief a lawyer can quote from in one call
Talk to a construction lawyer
When it’s lawyer’s work, go straight to a lawyer.
- Your lien deadline is inside two weeks
- A lien or claim has been registered against you
- You want to go after the directors personally
- We point you to an independent Ontario construction lawyer — and take no referral fee
Step 1: Know your deadline — and write down your last day
Liens live and die by two clocks, and they run in order. For contracts since July 1, 2018:
| Step | Deadline | What it means |
|---|---|---|
| Preserve | 60 days | Register your claim for lien on title (or give it to the clerk or ministry on public land). |
| Perfect | 90 more days | Start an action in the Superior Court and register a certificate of action on title, within 90 days after the last day the lien could have been preserved. |
| Keep it alive | 2 years | The action has to be set down for trial within two years of being started, or the perfected lien expires. |
What starts the 60 days
| If you are… | The clock runs from the earliest of… |
|---|---|
| The general contractor | publication of a certificate of substantial performance · completion · abandonment · termination of the contract |
| A sub or supplier | publication of a certificate (for work supplied before it) · your last day of supply · your subcontract being certified complete · abandonment or termination of the main contract |
- Write down your last day of real work on every job, the day it happens: what you did and what proves it. Courts decide it largely from your invoices — a visit you never invoiced is weak evidence.
- Callbacks don’t restart the clock. Coming back to fix a deficiency, warranty work, or picking up tools usually doesn’t count.
- Watch for certificates. Since January 2026 certificates of substantial performance are published on the Daily Commercial News, Link2Build or Ontario Construction News. Once published, the clock can start for everyone who supplied before it — seen or not.
- Old contracts, old rules. If the main contract or procurement started before July 1, 2018, the old Construction Lien Act and its 45-day clock apply.
Step 2: Gather the details — owner, land, work, dates
Liens fail on wrong details far more often than on the law. Pull the parcel register on OnLand ($36.50) and collect these before anyone registers anything:
Legal description + PIN
The property’s legal description and PIN — not just the street address. If your work went into more than one parcel, describe every one.
Every registered owner
The exact names on title, not the name on the sign or the person who hired you. If there’s any doubt who the owner is, name every candidate and let the lawyer decide.
Work, price, balance
A short description of what you supplied, the contract or subcontract price, and the unpaid balance.
First and last supply
These decide whether you’re still inside the 60-day window.
Spend $8 on the Ontario Business Registry profile of whoever hired you too — you need its exact legal name, and its directors’ names if this turns into a trust claim.
Before you register: the written notice of lien
A written notice of lien (Form 1) goes to the payer above you — usually the owner or the GC. It forces them to hold back enough to cover your claim from what they pay down the chain, and it can stop a construction lender’s priority on further advances. That can freeze the money where you can reach it.
How much to lien for
Lien the value of what you supplied and haven’t been paid for, plus approved extras, minus credits for work not done and acknowledged deficiencies. Include holdback owed to you. Don’t lien the full contract price, interest, head-office markup, profit on work you never did, or materials that never arrived.
Step 3: Register (preserve) the lien
Liens on private land are registered electronically through Teraview, Ontario’s land registration system. Teraview uses licensed accounts and paper registration is only accepted in limited cases, so in practice:
- Most liens are registered by a construction lawyer. The Law Society has treated preparing and registering liens as lawyers’ work.
- Online lien-registration services exist. They run on what you type in — Ontario lawyers have warned that a wrong owner name or a missed trigger can sink the lien, and once it’s registered you can’t simply refile to fix it.
- Register well before day 60. The system stamps the date and time — your proof you were in time. Don’t call a lawyer on day 59.
- Public jobs are different. On municipal or provincial land the claim is given to the clerk or ministry and attaches to the holdback, not the land. Federal land can’t be liened — look for a payment bond.
Step 4: Perfect the lien within 90 days
Preserving puts the lien on title; perfecting makes it enforceable. Within 90 days after the last day you could have preserved, the lien has to be perfected: an action started in the Superior Court of Justice and a certificate of action registered on title. A company needs a lawyer for this part.
A lien can’t be enforced in Small Claims Court — lien actions start in the Superior Court.
What it costs to register a lien
Registration fee
$85.00 to register a document electronically (fee schedule from November 3, 2025), plus $36.50 for the parcel register.
Register it
Roughly $800 to $2,500 to prepare and register a claim for lien.
Perfect it
Another $2,000 to $5,000 or more if it has to be perfected. Taking one to trial can run $10,000 to $50,000 or more.
Is it worth liening?
A lien is a tool, not a principle. The right question is what you’ll end up with.
| You’re owed | Settles after registering | Has to be perfected | My read |
|---|---|---|---|
| $5,000 | about $2,500–$4,200 | could go to zero | Usually not. A letter, adjudication or Small Claims nets more. |
| $15,000 | about $12,500–$14,200 | about $7,500–$12,000 | Worth it if the payer is stalling and the owner is solid. |
| $40,000 | about $37,500–$39,200 | about $32,500–$37,000 | Usually yes. Often the best $3,000 you’ll spend. |
Amount owed minus typical registration and perfection costs; leaves out your own time. Compare every route on the not-paid page.
What happens after you file
- The owner reacts. Owners who need to sell, refinance or draw on a loan usually pay, settle, or lean on the GC once a lien lands.
- Or they vacate it. The court will order the lien off title once enough money or security is paid in — generally the amount claimed plus security for costs (25%, capped at $250,000), or another amount the court finds reasonable.
- A vacated lien isn’t lost. Your claim moves from the land to the money or bond in court. You still have to perfect and pursue it — but now there’s money sitting there with your name on the claim.
- Most cases settle. When you’re paid, register a discharge promptly.
Things people get wrong
Not just contractors
Subs at any tier, suppliers, rental outfits, workers, architects and engineers can lien if their work went into the improvement. Since 2026, unpaid designers can lien even if construction never starts.
The clock doesn’t restart
Deficiency and warranty visits usually don’t extend your deadline. Count from your last day of real supply.
Whose interest you lien
On a tenant improvement your lien usually attaches to the tenant’s lease, not the landlord’s building, unless the landlord got written notice.
You can’t pre-waive
A contract clause that tries to make you give up lien rights in advance is void under the Act. You can release a lien after you’re paid.
Keep current: the 2018 and 2026 changes
The Construction Lien Act became the Construction Act in 2018, with the 60-day and 90-day periods. Prompt payment and adjudication arrived October 1, 2019. Amendments in force January 1, 2026 added mandatory annual holdback release, tightened proper-invoice rules, let lien and trust claims be combined in one action, and opened liens to unpaid designers. The core 60/90 deadlines didn’t change. See the Ontario Construction Act, explained and holdback and the 2026 annual release.
Do you need a lawyer?
You can do most of the homework yourself — your date, the parcel register, the amount, the details. But registering through Teraview and perfecting in the Superior Court are realistically lawyer’s work, and a defective or inflated lien can come back at you. Doing it without help is like building a skyscraper with a butter knife: possible, but the room for costly error is enormous.
The Ontario Lien Handbook walks through every step — including a lien prep worksheet that turns a lawyer’s first call into a short one — and covers what to do if a lien is registered against you.
Questions trades ask
How long do I have to register a construction lien in Ontario?
For contracts entered into after June 30, 2018: 60 days from the earliest of your last supply, publication of a certificate of substantial performance, or completion, abandonment or termination of the contract. Contracts or procurements from on or before June 30, 2018 run on the old Construction Lien Act's 45 days.
Can I lien for a cash job with no written contract?
Possibly — the lien comes from supply, not paper. But proving the price and the work without paper is hard, and an unsupported lien can cost you damages and costs.
How much can I lien for?
The value of what you supplied and haven't been paid for, plus approved extras, minus credits for work not done and acknowledged deficiencies. Not the full contract price, interest, head-office overhead, lost profit or undelivered materials.
What happens if I lien for too much?
You can be liable for the other side's damages and costs, and the court can reduce or discharge the lien. Lawyers registering liens can face costs too, so expect them to want proof.
Can I register a lien myself online?
Liens are registered electronically on title, normally through a lawyer. The Law Society has treated preparing and registering liens as lawyers' work, and a bad lien is hard to fix.
What does a lawyer charge to register a lien?
Roughly $800 to $2,500 to register, and $2,000 to $5,000 or more to perfect. Taking one to trial: $10,000 to $50,000 or more.
Not legal advice. This is general information from an Ontario builder, current to October 2026. Your dates and rights depend on your contract and your facts — confirm them with an Ontario construction lawyer before you rely on them. Read the Construction Act on ontario.ca.
Getting paid: the full set of guides
Ready to get paid? Pick the help that fits.
Start with the handbook — it walks you through filing a lien, or fighting one, step by step. Want a builder to go through your own paperwork? The Builder Payment Review comes back within two business days.
The Ontario Lien Handbook
File a lien yourself — or get one off your title.
- Step by step: your deadline, the parcel register, the amount, the claim for lien
- What you can do yourself and what needs a lawyer — so you pay for less of it
- Lien on your house or job? Your real exposure, a validity checklist and 8 ways out
- 6 letters, 4 worksheets and a numbers card to tape on the wall
Builder Payment Review
A builder goes through your own paperwork and tells you where you stand.
- The Ontario Lien Handbook included
- Your deadlines worked out from your own dates
- Every document rated line by line: what you can prove and what you can’t
- The excuse you were given, tested against what the Act requires of them
- The amount you can defend claiming — extras, holdback, interest
- Every route ranked by what it would net you, and a 14-day plan
- A two-page brief a lawyer can quote from in one call
Talk to a construction lawyer
When it’s lawyer’s work, go straight to a lawyer.
- Your lien deadline is inside two weeks
- A lien or claim has been registered against you
- You want to go after the directors personally
- We point you to an independent Ontario construction lawyer — and take no referral fee
More on builder problems and liens
Reviewed and updated October 2026. Costs on this site are Ontario ranges, not quotes; code references are to the Ontario Building Code in force at the date above.