Floor Joist and Beam Span Tables Ontario (2027)
Ontario Building Code 2024 span tables for 2x8, 2x10 and 2x12 floor joists and built-up beams, in feet and inches, with a free calculator and a builder's notes.

How Far Can A Floor Joist Span? The Ontario Tables, In Plain Feet And Inches
The Ontario Building Code prints its span tables in metres, for four groups of lumber species, across about seventy rows each. Almost every house in this province is framed with one of them: spruce-pine-fir, No. 1 and No. 2 grade. So here is that one, converted to feet and inches, with a calculator and a builder’s notes on where people get into trouble.
Let Me Set Your Expectations First
A span table tells you the longest joist the Code will allow. It does not tell you the floor will feel good. A joist at its maximum span passes inspection and still lets the china cabinet rattle when the dog walks by.
So read these numbers as a limit, not a target. When I frame a floor I like to stay a foot or so inside the table, or go one size deeper. Lumber is cheap compared to listening to a bouncy floor for thirty years.
One more thing. I build houses. I am not an engineer, and nothing here replaces your permit drawings. The tables below are copied from the Code and checked line by line, but your building department and your drawings have the last word.
Floor Joist Span Table: The Everyday Case
This is the table for a normal house floor: spruce-pine-fir No. 1 or No. 2, with strapping nailed to the underside of the joists. A drywall ceiling fastened straight to the joists counts in place of the strapping, which is why this is the table most finished floors fall under.
| Joist | 12″ on centre | 16″ on centre | 24″ on centre |
|---|---|---|---|
| 2×6 38 x 140 mm | 9′-6″ 2.92 m | 8′-10″ 2.71 m | 8′-2″ 2.49 m |
| 2×8 38 x 184 mm | 11′-7″ 3.54 m | 11′-0″ 3.36 m | 10′-5″ 3.20 m |
| 2×10 38 x 235 mm | 13′-8″ 4.17 m | 12′-11″ 3.96 m | 12′-4″ 3.77 m |
| 2×12 38 x 286 mm | 15′-7″ 4.75 m | 14′-9″ 4.52 m | 14′-1″ 4.30 m |
Source: 2024 Ontario Building Code, Span Table 9.23.4.2.-A, “with strapping”. Spans are clear spans between supports. The Code figure is the metric one; the feet and inches are rounded down to the inch.
With Bridging Instead
Cross bridging or solid blocking between the joists, in rows no more than 2,100 mm (about 6′-10″) apart, stiffens the floor and buys you a little more span.
| Joist | 12″ on centre | 16″ on centre | 24″ on centre |
|---|---|---|---|
| 2×6 38 x 140 mm | 10′-3″ 3.14 m | 9′-4″ 2.85 m | 8′-2″ 2.49 m |
| 2×8 38 x 184 mm | 12′-6″ 3.81 m | 11′-8″ 3.58 m | 10′-8″ 3.27 m |
| 2×10 38 x 235 mm | 14′-6″ 4.44 m | 13′-8″ 4.17 m | 12′-10″ 3.92 m |
| 2×12 38 x 286 mm | 16′-5″ 5.01 m | 15′-5″ 4.71 m | 14′-6″ 4.42 m |
With Bridging And Strapping Together
This is the best the Code gives sawn lumber: bridging between the joists and strapping under it.
| Joist | 12″ on centre | 16″ on centre | 24″ on centre |
|---|---|---|---|
| 2×6 38 x 140 mm | 10′-3″ 3.14 m | 9′-4″ 2.85 m | 8′-2″ 2.49 m |
| 2×8 38 x 184 mm | 13′-1″ 3.99 m | 12′-2″ 3.72 m | 10′-8″ 3.27 m |
| 2×10 38 x 235 mm | 15′-1″ 4.60 m | 14′-0″ 4.29 m | 13′-1″ 4.00 m |
| 2×12 38 x 286 mm | 16′-11″ 5.17 m | 15′-9″ 4.82 m | 14′-8″ 4.49 m |
Source: 2024 Ontario Building Code, Span Table 9.23.4.2.-A, “with bridging” and “with strapping and bridging”. Strapping is 19 x 64 mm (a 1×3) nailed to the underside; bridging is 19 x 64 mm or 38 x 38 mm cross bridging, or 38 mm solid blocking where both are used.
Look at the 2×6 row
The 2×6 and 2×4 numbers do not change with bridging at 24″ spacing. Bridging stops a floor from bouncing, and a short shallow joist was never limited by bounce in the first place. It was limited by strength. No amount of blocking makes a small stick stronger.
Joist Span Calculator
Enter the clear span between supports, not the length of the lumber you plan to buy.
Spruce-pine-fir No. 1 and No. 2, residential floor loads, no concrete topping. For a deck, use the deck joist span calculator instead; decks carry snow and the rules are different.
Now The Beam Under Those Joists
The joists have to sit on something. In most houses that is a built-up wood beam down the middle of the basement: three, four or five pieces of 2×8, 2×10 or 2×12 nailed together, sitting on posts.
How far that beam can go between posts depends on how much floor it is carrying. The Code calls that the supported length, and it is half the joist span on one side of the beam plus half the joist span on the other. If the joists run 13′-9″ on each side of the beam, the supported length is 13′-9″, which is 4.2 m.
Beam Carrying One Floor
| Built-up beam | Joists 9′-10″ each side supported length 3.0 m | Joists 11′-9″ each side 3.6 m | Joists 13′-9″ each side 4.2 m | Joists 15′-8″ each side 4.8 m |
|---|---|---|---|---|
| 3-ply 2×8 | 9′-4″ 2.85 m | 8′-7″ 2.63 m | 8′-0″ 2.44 m | 7′-5″ 2.28 m |
| 4-ply 2×8 | 10′-3″ 3.14 m | 9′-8″ 2.95 m | 9′-2″ 2.80 m | 8′-7″ 2.63 m |
| 5-ply 2×8 | 11′-1″ 3.38 m | 10′-5″ 3.18 m | 9′-10″ 3.02 m | 9′-5″ 2.89 m |
| 3-ply 2×10 | 11′-6″ 3.52 m | 10′-6″ 3.22 m | 9′-9″ 2.98 m | 9′-1″ 2.79 m |
| 4-ply 2×10 | 13′-1″ 4.01 m | 12′-2″ 3.71 m | 11′-3″ 3.44 m | 10′-6″ 3.22 m |
| 5-ply 2×10 | 14′-2″ 4.32 m | 13′-3″ 4.06 m | 12′-7″ 3.84 m | 11′-9″ 3.60 m |
| 3-ply 2×12 | 13′-5″ 4.09 m | 12′-2″ 3.73 m | 11′-4″ 3.46 m | 10′-7″ 3.23 m |
| 4-ply 2×12 | 15′-5″ 4.72 m | 14′-1″ 4.31 m | 13′-1″ 3.99 m | 12′-2″ 3.73 m |
| 5-ply 2×12 | 17′-2″ 5.25 m | 15′-9″ 4.82 m | 14′-7″ 4.46 m | 13′-8″ 4.17 m |
Beam Carrying Two Floors
Put a second storey on top and the same beam goes a lot less far.
| Built-up beam | Joists 9′-10″ each side supported length 3.0 m | Joists 11′-9″ each side 3.6 m | Joists 13′-9″ each side 4.2 m | Joists 15′-8″ each side 4.8 m |
|---|---|---|---|---|
| 3-ply 2×8 | 7′-1″ 2.16 m | 6′-5″ 1.97 m | 5′-11″ 1.82 m | 5′-7″ 1.71 m |
| 4-ply 2×8 | 8′-2″ 2.49 m | 7′-5″ 2.27 m | 6′-11″ 2.11 m | 6′-5″ 1.97 m |
| 5-ply 2×8 | 9′-1″ 2.79 m | 8′-4″ 2.54 m | 7′-8″ 2.35 m | 7′-2″ 2.20 m |
| 3-ply 2×10 | 8′-7″ 2.64 m | 7′-10″ 2.41 m | 7′-3″ 2.23 m | 6′-10″ 2.09 m |
| 4-ply 2×10 | 10′-0″ 3.05 m | 9′-1″ 2.78 m | 8′-5″ 2.57 m | 7′-10″ 2.41 m |
| 5-ply 2×10 | 11′-2″ 3.41 m | 10′-2″ 3.11 m | 9′-5″ 2.88 m | 8′-9″ 2.69 m |
| 3-ply 2×12 | 10′-0″ 3.06 m | 9′-1″ 2.79 m | 8′-5″ 2.59 m | 7′-11″ 2.42 m |
| 4-ply 2×12 | 11′-6″ 3.53 m | 10′-7″ 3.23 m | 9′-9″ 2.99 m | 9′-1″ 2.79 m |
| 5-ply 2×12 | 12′-11″ 3.95 m | 11′-10″ 3.61 m | 10′-11″ 3.34 m | 10′-2″ 3.12 m |
Source: 2024 Ontario Building Code, Span Tables 9.23.4.2.-H (one floor) and 9.23.4.2.-I (two floors), spruce-pine-fir No. 1 and No. 2. Spans are clear spans between supports. Minimum bearing at each end is 76 mm (3″), or 114 mm (4 1/2″) for a 3-ply beam with a supported length over 4.2 m. With a concrete topping of up to 51 mm on the floors, the Code has you multiply the beam span by 0.8.
A worked example
A house 27′-6″ wide with a beam down the centre has joists spanning about 13′-9″ on each side. Supported length: 4.2 m. Carrying one floor, a 3-ply 2×10 beam can go 9′-9″ between posts, a 4-ply 2×10 can go 11′-3″, and a 5-ply 2×12 can go 14′-7″. Want the posts farther apart than that? Now you are into LVL or steel, and somebody else’s tables.
Beam Span Calculator
For a beam with joists on both sides, enter both spans. For a beam with joists on one side only, enter 0 for the other.
Built-up spruce-pine-fir No. 1 and No. 2 beams from Span Tables 9.23.4.2.-H, -I and -J. In-between supported lengths are worked out by straight-line interpolation, which the Code allows. This covers a beam carrying floors only. A beam that also carries a roof, a bearing wall that does not line up, or a post from above is a different animal.
Where Homeowners Go Wrong!
- They measure the lumber, not the span. Span is the clear distance between supports. A 14-foot joist sitting on a beam and a foundation wall does not span 14 feet.
- They forget the topping. A concrete or gypsum topping for in-floor radiant heat is heavy. The Code says the joist spans in the everyday table have to come down, or the spacing has to tighten, to carry it. I have put radiant in a lot of floors, and the framing gets decided before the tubing does.
- They put a point load on a table built for even loads. Every number on this page assumes weight spread evenly across the floor. A stone kitchen island, a cast iron tub, an aquarium or a post from the floor above is not spread evenly.
- They use these tables for engineered joists. I-joists and floor trusses span farther, and they come with the manufacturer’s own tables and layout. See I-joists vs floor trusses.
- They let the plumber decide. A joist with a big notch in the bottom for a drain is not the joist in the table any more. Holes and notches have limits. Find them out before the plumber finds them out for you.
- They take out a wall. That wall in the middle of the basement may be why the joists upstairs are only 2×8. Before any wall comes out, read what goes into removing a load-bearing wall.
What The Inspector Looks For
At the framing inspection the inspector is comparing what you built to what the permit drawings say. On the floor that comes down to a short list.
- The grade stamp on the lumber. No. 2 or better means the stamp says so, not that it looked straight at the yard.
- Joist size and spacing against the drawings.
- The beam: number of plies, how it is nailed together, and whether the joints land over posts.
- Bearing at the ends of beams and joists, and what the posts sit on.
- Bridging, blocking or strapping where the drawings call for it.
- Notches and holes from the trades.
Our framing inspection checklist goes through the whole visit, and the page on building permit drawings explains what has to be on paper before you start.
When The Tables Run Out, Call An Engineer
The span tables cover ordinary houses built the ordinary way. Step outside them and the Code wants the framing designed, which in practice means a stamped drawing. You are outside the tables when:
- the span is longer than anything in the table for your lumber;
- a beam’s supported length is over 6.0 m;
- a beam carries a roof, a wall above that does not stack, or a concentrated load;
- the floor carries more than a normal house load, such as a library wall, a hot tub or a concrete floor;
- you are cutting a big opening in a floor for a stair that was not on the original drawings.
It is not as expensive or as slow as people fear, and it is a great deal cheaper than fixing a sagging floor. Here is when a house needs a structural engineer in Ontario, and our page on beams and structural changes covers the usual renovation cases.
Questions I Get Asked
How far can a 2×10 floor joist span in Ontario?
Spruce-pine-fir No. 1 or No. 2 with strapping or a drywall ceiling: 13′-8″ at 12″ on centre, 12′-11″ at 16″ and 12′-4″ at 24″. With bridging and strapping together it is 15′-1″, 14′-0″ and 13′-1″.
How far can a 2×8 floor joist span?
With strapping or a drywall ceiling: 11′-7″ at 12″ on centre, 11′-0″ at 16″ and 10′-5″ at 24″.
How far can a 2×12 floor joist span?
With strapping or a drywall ceiling: 15′-7″ at 12″ on centre, 14′-9″ at 16″ and 14′-1″ at 24″. With bridging and strapping together: 16′-11″, 15′-9″ and 14′-8″.
Is 12″ spacing worth it over 16″?
On a 2×10 it buys you about nine inches of span and a third more lumber. If you only need a few more inches, going one size deeper is usually the cheaper way to get a stiffer floor.
Are these the same as the deck span tables?
No. A deck sits outside, carries snow and is usually built from pressure-treated lumber, and many towns publish their own deck guides. Use our deck joist and beam span page for decks.
Do I need a permit to change floor framing?
Changing structure, which includes joists, beams and bearing walls, needs a building permit in Ontario. Replacing flooring on top of the joists does not.
Sources And Further Reading
- 2024 Ontario Building Code Compendium, Part 9: the span tables themselves, plus the rules on strapping, bridging and concrete topping.
- City of North Bay span table handout: a building department’s own printout of the spruce tables, in metric and imperial.
- Canadian Wood Council: span books and design tools for wood framing.
Not Sure Your Framing Will Pass?
Work out what the job should cost, then have the drawings looked at before the lumber is delivered. It is the cheapest inspection you will ever have.
Information only. Not engineering advice. Span figures are for spruce-pine-fir No. 1 and No. 2 under the 2024 Ontario Building Code; the metric values govern, and other species, grades and loads have different spans. Confirm everything against your permit drawings and your building department.